General News
20 November, 2026
Burketown Airport reopens
BURKETOWN Airport has officially reopened following a $24.4 million upgrade, largely funded by the State and Federal Governments.

The repairs have addressed significant damage caused during the 2022-23 disaster season, restoring a critical transport link for the remote Gulf community.
With all roads in and out of Burketown cut off for months at a time during the wet season, an operational airfield is essential to ensure the safety and wellbeing of the community.
Central to the reconstruction project was an upgraded airstrip designed to increase access and reliability in all conditions.
The new runway pavement includes triple blend stabilisation using lime, cement and fly ash, and it has been raised 400mm, placing it above both the 2023 flood level and the site’s historical maximum flood level.
Upgrades to airfield lighting, drainage and service roads have also been completed.
Royal Flying Doctor Service and Savannah Aviation charter began using sections of the new runway in September, while Rex Airlines was set to commence commercial flights at the airport from Monday.